Which crane and how long does it take to install ventilation equipment weighing up to 700 kg over the entire roof on several sections of our residential complex? The roof height of the lowest section is 55 meters, and the highest is 74 meters.


Answer :

For these installation works, it is necessary to develop a PPR PS (PPRK), which will include flow charts (graphic part of the project), which will show how many sites are required for installing a truck crane and how many mounting points a truck crane can mount from each parking lot.

Also, in the process of developing a project, the designer will select the optimal truck crane that will cope with this work and minimize the number of parking lots. In the zone of each parking lot of the truck crane, a place for storing equipment for installation will be determined.

It should be especially noted that if there is an underground parking in the area of ​​the truck crane installations, the help of surveyors will be required to display the points of the location of the supporting columns of the parking during the design. The project will determine the need to strengthen the parking floor with the help of screw jacks in places that will fall into the installation zone of the truck crane supports, if there are no support columns in this area.

A truck crane with a transport weight of up to 50 tons can pass over the underground parking, since the overlap of any parking lot is designed for a fire engine with this weight to drive on it. The maximum truck crane with such a transport weight is 100 tons LIEBHERR LTM 1100-4.1 (4.2), or a similar truck crane with 4 axles. If you need a truck crane with a large weight (5 or more axles), then you need to request the characteristics of the parking overlap from the developer, or consider the passage and installation of the crane outside the underground parking area.

To develop a PPRK, our designer will need a roof plan for each section with an indication of the installation locations, as well as a part of the master plan with this residential complex and the adjacent territory. Files in DWG format will make our task easier and speed up the development of PPR PS (PPRK). After the development of the PPRK, we will be able to answer how long it will take to move the crane and install / dismantle the lattice jib, if required.

Slinging, lifting and installing equipment at each point usually takes from 5 to 15 minutes and more depends on the team of installers of this equipment. After preparation of sites, access roads and storage of equipment for installation, you should take into account the wind forecast when choosing dates for installation / ordering a truck crane from our managers.

The wind speed during these works should not exceed 10 m / s. If during the installation process the wind speed or wind gusts exceed 10 m / s, the driver will be forced to temporarily suspend the work until the wind subsides within the permissible range.

CONTACTS

  • 196626, St. Petersburg,
    p. Shushary, st. Pushkinskaya 25 building 2
  • +7 (812) 309-70-07 (multichannel t / f)
  • +7 (911) 927-52-92 , 927-89-00 , 929-99-97
    (department: mobile rental cranes)
  • Email: This email address is being protected from spambots. You need JavaScript enabled to view it.
Up