Installation of cable-stayed system Volgograd Arena
09.2017
The Volgograd-Arena stadium is designed for 45 thousand spectators, it is being built for the 2018 FIFA World Cup.
At the moment, the builders have completed the installation of a unique cable-stayed system for the roof of the stadium. The large-scale structure, the only one in Russia, is supported by steel ropes.
Our worked at the "Volgograd Arena" stadium truck crane 200t . LIEBHERR LTM 1200 - 5.1, which carried out the installation of the facade steel structures and the lifting of the unique cable-stayed system of the stadium roof. Our aerial platform 45m also took part in the construction. She lifted the assemblers who worked in tandem with our crane. Subsequently, a membrane roof was installed on this cable-stayed system.
I would like to dwell in more detail on the work of the LIEBHERR LTM 1200-5.1 truck crane during the construction of the Volgograd Arena football stadium».